8,4km of sewers in Parow Valley successfully rehabilitated

12 June 2025

Two major sewer rehabilitation projects in Parow Valley, launched in February 2025, have been successfully completed ahead of schedule. These upgrades form part of the Water and Sanitation Directorate’s proactive pipe replacement programme, which aims to rehabilitate or replace up to 100km of sewer infrastructure annually across Cape Town.

The work was undertaken as part of the Mayor’s Priority Programme (MPP), through which Water and Sanitation has expanded its Sewer and Water Pipe Replacement Programme. A total of R523 million has been allocated to infrastructure maintenance and pipe replacement during the 2024/25 financial year.

Due to the deteriorating condition of sewer infrastructure in the area, two separate rehabilitation projects were implemented.

  • Project 1: Rehabilitated 4,24km of 150mm diameter sewer mains across Market, Connaught, Rissik, Philips, Taylor, Potgieter, Prinsloo, Eland, Frederick, De Villiers, Jacaranda, Piet Retief, Hartbees, Paul Kruger, and Van Wyk Streets.
  • Project 2: Rehabilitated 4,2km of 150mm to 225mm sewer mains in Joubert, Connaught, Rissik, Willie Van Der Poel, Taylor, Prinsloo, Moore, Frederick, De Villiers, Vlei, Riley, and Piet Retief Streets.
Some streets were shared between the two projects due to their length. 


Both projects were completed on 14 April 2025, well ahead of the anticipated completion date in June.

The rehabilitation used a cured-in-place pipe (CIPP) lining method, a widely adopted trenchless technique that restores ageing sewer mains with minimal disruption to the surrounding area. This method included:

  • Isolating sections of the pipeline;
  • Over-pumping or bypassing flows;
  • Inserting a resin-saturated liner into the host pipe;
  • Curing the liner in place;
  • CCTV inspections;
  • Robotic cutting; and
  • Final pipe testing.

‘Rehabilitating ageing infrastructure is part of our broader strategy to ensure more reliable sanitation services across the city. While infrastructure upgrades are essential, preventing blockages also depends on responsible usage. Flushing items like nappies, rags, and other foreign materials causes avoidable sewer overflows. These items should never be flushed or disposed of down drains,’ said Mayoral Committee Member for Water and Sanitation, Councillor Zahid Badroodien. 

Residents can help reduce sewer overflows:

  • Don't flush anything other than human waste and toilet paper. Anything else will block the pipes. See www.capetown.gov.za/blocked-sewers.

  • Use only the City's solid waste services provided to get rid of your waste.

  • Report sewer blockages and overflows using one of the City's official channels.

  • Report vandalism of the sewer system and stolen or missing sewer manhole covers.

  • Use the City's drop-off facilities to get rid of recyclables. See https://bit.ly/3mhagVh

End


 

Published by:
City of Cape Town, Media Office

You may also be interested in

placeholder

Ref 1500158681 - Rezoning and permanent departures

7 August - 11 September 2026, Vasco Estate (Goodwood)

placeholder

Ref 1500163830 - Rezoning and removal of restrictive title deed condition

7 August - 9 September 2026, Bene Township (Somerset West)

You have disabled JavaScript on your browser.
Please enable it in order to use City online applications.